Paris (France) (AFP) – Two and a half years late, the new SNCF TGV finally carries out its first commercial service on Friday morning, between Paris and Marseille, with a multitude of technical innovations on board to support the high speed of the 21st century.

Published on: 06/11/2026 - 00:48

Launching with its first passengers a week after a terrible accident in Spain which devastated European railways by causing the death of 69 people, the new TGV manufactured by Alstom will not run faster than the most recent trains circulating on the French network, i.e. 320 km/h.

But this TGV, the only one in the world to travel at such speed with two floors, aims to be more comfortable, modular, ecological and economical than its predecessors.

Thanks in particular to its tapered nose and reinforced aerodynamics, it promises to consume 20% less energy by accommodating up to 20% more passengers.

The new trains will gradually replace, over around ten years, the existing fleet, the oldest of which date from the 1990s.

Of the 160 units ordered by SNCF for more than 5 billion euros, 100 are intended for the French market, 15 for France-Belgium connections, 30 for the Eurostar network and around fifteen for the Italian market where SNCF intends to develop.

On the Paris-Marseille axis, it will be in head-on competition with the Frecciarossa (red arrow) of the Italian Trenitalia, built by Hitachi.

“Mystery shoppers”

In 2020, during the presentation of the first cabin at the Alstom factory in La Rochelle, a senior SNCF official hoped that it would run "for the Paris Olympic Games in 2024".

But industrial delays linked to the covid-19 period quickly put this objective out of reach.

After reaching the speed of 320 km/hour for the first time on September 14, 2023, SNCF and Alstom then bet on entry into service in 2025, before pushing it back again to 2026 due to technical disputes and the extent of the tests to be validated to obtain approval.

In total, three and a half years passed between the first circuit tests in the Czech Republic in December 2022, and final approval in May 2026 by France and, for safety, by the European Railways Agency (ERA).

Since this summer, SNCF has carried out the first running-in runs without commercial passengers on board. 1,600 “mystery shoppers”, including SNCF and Alstom employees, noted their experience.

In terms of innovations, the SNCF especially emphasizes the modularity of the new train, which is why it has long called it TGV “M”.

It can increase from 8 to 9 cars and the number of first or second classes can vary depending on the destinations or the seasons, an element considered "strategic" for a train expected to run for several decades.

Battery and energy storage

On the environmental side, the train emits 50% less CO2 per passenger than the first TGV launched in 1981. It uses 25% of recycled materials and has a recyclability rate of 97%.

On the economic side, the 25,000 pieces of information analyzed in real time should enable it to use predictive maintenance, which shortens workshop downtime and reduces maintenance costs by 30%.

Passengers in wheelchairs will be able to board without assistance, although there will always be agents present if necessary. On the Paris-Marseille axis, the new TGV will offer 573 seats compared to 500 currently.

A train will be able to transport up to 700 people in a single class, with the promise of more room for legs, for luggage, more bicycle spaces, more comfortable seats, a two-story bar and wifi "at the best standard", but always dependent on the coverage of mobile operators on the network.

Major progress in adapting to global warming: it is equipped with an energy storage battery, which will allow it to continue its route to the nearest station in the event of a catenary break in the middle of nowhere due to a heatwave, like last summer.